On Monday, the wind turbine maker Suzlon Group said that it has completed the commission of 50.40 mega watt (MW) wind power turnkey project for Ostro Energy Pvt Ltd owned by Actis.
It said in a BSE filing that “Suzlon has been responsible for the entire project lifecycle, from development, construction to commissioning and has also been contracted to undertake operations and maintenance services of the project for 12 years… “The project will provide electricity to over 28,000 homes and curb 0.10 million tonnes of CO2 emissions annually.”
The project that includes 24 WTGs (Wind Turbine Generators) of 2.1 MW each, is situated in Tejuva, Jaisalmer, Rajasthan.
It further said that “It forms an integral part of Suzlon’s Jaisalmer wind park, billed to be the country’s largest wind park with a cumulative capacity over 1300 MW.”